LENGTH (mm) |
HEIGHT (mm) |
WIDTH (mm) |
WEIGHT (mm) |
|
---|---|---|---|---|
Size 1 | 600 | 200 | 100 | <8.0 |
Size 2 | 600 | 200 | 150 | <13.5 |
Size 3 | 600 | 200 | 200 | <18.5 |
Brick (225mm) | AAC (200mm) | |
---|---|---|
Material | ||
Blocks | 112.00 | 75.00 |
Wastage | 0.05 | 0.03 |
Cement (50kg Bags) | 0.40 | 0.52 |
Sand (Cubes) | 0.03 | 0.03 |
Water (gals) | 75.00 | 25.00 |
Labour | ||
Days mason | 1.00 | 1.00 |
Days Un Skill Labourer | 2.00 | 1.00 |
Brick (225mm) | AAC (200mm) | |
---|---|---|
Material | ||
Bricks | 1,090.00 | 75.00 |
Wastage | 0.05 | 0.03 |
Cement (50kg Bags) | 3.00 | 0.08 |
Sand (Cubes) | 0.20 | 0.01 |
Water (gals) | 115.00 | 40.00 |
Labour | ||
Days mason | 2.25 | 1.40 |
Days Un Skill Labourer | 3.75 | 1.40 |
Brick (225mm) | AAC (200mm) | |
---|---|---|
Material | ||
Bricks | 550.00 | 75.00 |
Wastage | 0.05 | 0.03 |
Cement (50kg Bags) | 1.30 | 0.04 |
Sand (Cubes) | 0.10 | 0.00 |
Water (gals) | 50.00 | 25.00 |
Labour | ||
Days mason | 1.50 | 1.00 |
Days Un Skill Labourer | 2.00 | 1.00 |